How should a contractor approve a subcontractor invoice?

Use one subcontractor invoice approval process to match the bill to the agreement, verify completed work, handle changes and retainage, and preserve the payment record.

Por Kyle Burt·Founder, Contractor Systems·20 de noviembre de 2026·7 min de lectura

A general contractor reviewing plans and job records before approving subcontractor work.

A subcontractor invoice is a request for payment. It is not proof that the amount is due.

That distinction matters when an invoice reaches accounting before the project manager has confirmed the work, a field change is still sitting in a text thread, or the bill includes materials nobody can locate. Paying it anyway creates bad job-cost data and makes the next invoice harder to review. Holding it without a clear reason creates a different problem.

Use one subcontractor invoice approval process for both sides. The subcontractor should know what evidence is required. Your team should know who verifies the field work, who checks the agreement, who approves the amount, and what blocks payment.

This is an operating framework, not legal or accounting advice. Payment deadlines, retainage, lien waivers, notices, and allowed deductions vary by contract and jurisdiction. Have the rule reviewed for the states and projects where you work.

Start with the agreement, not the invoice total

Pull the signed subcontract or purchase order before reviewing the bill. The invoice should match the agreement on the legal payee, job, scope, price, payment schedule, retainage, tax treatment, approved expenses, and billing requirements.

For a fixed-price scope, check which milestone the subcontractor says is complete. For time-and-material work, check the agreed labor rates, hours, material costs, equipment charges, markup, and required backup. For a unit-price agreement, verify the installed quantity and the rate.

A clean first review should answer:

  • Which job and agreement does this invoice belong to?
  • What billing period or milestone does it cover?
  • Which work, materials, or approved changes are included?
  • What has already been billed and paid?
  • What retainage or holdback applies under the agreement?
  • What amount is requested now?

A generic line such as “electrical work, 50 percent” does not give the office enough to approve. The subcontractor should connect the request to the current scope or schedule of values.

The AIA’s G702 and G703 payment forms are built around that same reconciliation. They show completed and stored work, retainage, previous payments, change orders, and the current amount requested. A residential contractor does not need to use those exact forms, but those fields are a useful test for any progress invoice.

Separate field verification from office approval

Accounting can confirm the math. Accounting usually cannot confirm that the rough plumbing passed the agreed milestone or that the cabinets listed as delivered are actually on the job.

Assign field verification to the person close enough to see the work and authorized to accept it. That may be the project manager, superintendent, owner, or trade lead. The verifier should compare the invoice with the current scope and record:

  • Work completed through a specific date
  • Quantity or milestone verified
  • Photos, inspection results, delivery tickets, or daily records used
  • Open defects, incomplete items, or damage
  • Materials stored on site or off site
  • Corrections required before the next phase

The contractor daily job log can support that review, but do not turn a daily note into automatic approval. “Crew worked upstairs” is not the same as confirming the billed milestone.

Keep the roles clear. The field verifier confirms what exists. The office checks the agreement and calculations. The authorized approver decides what amount can move forward. One person may fill more than one role in a small company, but the record should still show which check was performed.

Treat stored materials as a separate claim

A subcontractor may bill for equipment or materials before installation. Do not approve that amount from a supplier quote alone.

Check what the agreement allows and collect evidence that answers:

  • What exactly was purchased?
  • Has the subcontractor paid for it or become obligated for it?
  • Where is it stored?
  • Is it labeled for this job?
  • Who carries the risk of loss or damage?
  • Can your company inspect the quantity and condition?
  • Has the same material appeared on an earlier invoice?

The AIA payment form includes stored materials as a separate amount rather than treating them as installed work. That is the right operating habit even when your own form is simpler. Stored, delivered, and installed are different statuses. Your job record should not blur them.

If the agreement does not address off-site storage, insurance, ownership, or inspection, stop and resolve that gap before approving a large material payment.

Match every extra to an approved change

Subcontractor invoices are a bad place to discover added work.

If the invoice includes a new line that is not in the original agreement, find the written authorization. Confirm the changed scope, price or pricing method, schedule effect, and person who approved it. Then connect the invoice line to the change number.

A field instruction may prove that someone asked for work. It does not prove that the person had authority to approve the cost. The contractor change-order process explains how to move a request through pricing, approval, field release, and billing.

When the extra is valid but the paperwork is incomplete, do not quietly edit the invoice to make the numbers fit. Put the item in an exception status, identify the missing approval, and give one person a deadline to resolve it. Approve the undisputed portion only when the agreement, accounting process, and applicable law allow partial approval.

Calculate retainage from the contract

Retainage should not become a percentage somebody remembers from the last project.

Use the rate and release conditions in the subcontract, then check the law that applies. Calculate it against the correct base. Approved stored materials, change work, or completed portions may receive different treatment under the agreement. Show the current retainage, prior retainage, and total held to date.

Do not use retainage as a vague punishment for every concern. If work is incomplete, defective, unsupported, or disputed, document that issue and the amount tied to it. A clear exception record is easier to resolve than one unexplained reduction.

The final release needs its own gate. Confirm the agreed completion status, accepted corrections, required closeout documents, warranty information, returned access items, and any waiver or release requirements before releasing the balance. The earlier subcontractor onboarding checklist should define this evidence before the first day of work.

Handle lien waivers by jurisdiction and payment status

Do not download one lien-waiver template and use it everywhere. Required forms and timing vary.

California provides a useful example of why the details matter. The Contractors State License Board distinguishes conditional and unconditional waivers for progress and final payments. Its guidance says a conditional progress waiver is used before the claimant has been paid and becomes effective only when payment is actually received. An unconditional progress waiver says the claimant has received the payment.

That is California-specific guidance, not a national rule. Use the form, timing, through-date, exceptions, and signer required where the project sits. Have counsel set the policy. The operating system should then show which document is required before payment, which is collected after payment, and what period it covers.

A waiver with the wrong through-date can be worse than no checklist because it creates false confidence. Match the job, claimant, payment amount, billing period, and exceptions before filing it.

Use visible invoice statuses

An invoice should never disappear into an email inbox labeled “waiting.”

Use statuses that tell the team what happens next:

  1. Received
  2. Agreement check
  3. Field verification
  4. Correction or backup needed
  5. Approved for a stated amount
  6. Scheduled for payment
  7. Paid
  8. Payment proof and required release filed

If you reject or reduce an amount, record the exact reason, supporting evidence, owner, and next action. Send the subcontractor a useful answer. “Not approved” starts another email chain. “Invoice 184 includes $2,400 for unapproved added framing; original milestone of $8,000 is verified; Dana is reviewing change request 07” gives everyone something to resolve.

Approval and payment should remain separate statuses. An approved invoice can still be waiting for the contractual payment date. A scheduled payment has not cleared. A cleared payment may still need proof and a required post-payment release.

Audit one invoice before the next payment run

Pick one subcontractor invoice scheduled this week. Trace it from the signed agreement through field evidence, approved changes, retainage calculation, waiver requirement, accounting entry, payment proof, and job-cost record.

If the office has to call three people to explain the number, the process is not ready to scale. Fix the missing field or handoff before the next invoice arrives.

Keep the job, cost, and payment records in the systems that own them. If customer information and field records break between the front office and your production software, review the Contractor Systems integrations and see the connected workflow. Then test the approval gate on one invoice before making it the standard for every subcontractor.

Sources